Why would a Bitcoin miner give up capacity to an AI tenant? In its review of third-quarter results, Blockhead argues that, for facilities able to make the switch, a contracted AI lease can earn more from a megawatt of power than Bitcoin mining. That is a comparison of particular facilities and assumptions—not a rule for every mine.

The value of a megawatt
According to MillionMiner data cited by Blockhead, hashprice—the daily revenue from one PH/s of mining capacity—fell from $40.24 on October 1 to $33.18 at the end of October 2026. MARA reported costs of $30.80 per PH/s per day, leaving a margin of about 7% at the later hashprice under its own measure.
Blockhead estimates that one megawatt used for mining would generate roughly $600,000–$800,000 a year at a $33 hashprice and equipment efficiency of 15–20 joules per TH. That is before approximately $350,000 in electricity costs, assuming $0.04 per kWh, and excludes depreciation.
By comparison, Core Scientific reported more than $700 million in annualized hosting revenue from 485 megawatts of billable capacity—about $1.44 million per megawatt. Blockhead says standard AI hosting contracts generally charge tenants separately for electricity. On these figures, the hosting charge is about 1.8–2.4 times the estimated mining revenue per megawatt. The comparison depends on the stated equipment, power-price and contract assumptions; it is not a guaranteed return from converting a site.

What changes for Bitcoin?
A miner’s exit does not change Bitcoin’s issuance schedule. As Blockhead notes, the protocol was issuing about 450 BTC a day regardless of which operator mined them. The nearer-term question is whether companies sell BTC they already hold to pay for new infrastructure.
Blockhead reports that MARA sold 17,488 BTC during the quarter, compared with 2,247 BTC it mined, and said it planned further sales to fund AI infrastructure and meet note obligations. Riot sold 10,599 BTC in the third quarter; Hut 8 sold about 3,100 BTC across the third quarter and October. Those sales total roughly 31,000 BTC, but the reporting periods differ and the figure includes coins held in company treasuries—not just newly mined BTC.
Mining capacity can also shift toward operators that remain. Blockhead reports that MARA’s energized hash rate rose 18% and its share of block rewards increased from 5.0% to 5.4%. If other miners leave, network difficulty adjusts to the capacity that remains. These company results alone do not establish a lasting change in network security.
AI hosting replaces some exposure to Bitcoin’s price and mining difficulty with dependence on tenants, financing and access to power. Converting a mining site also requires substantial capital: Blockhead reports that Core Scientific spent $954.2 million on capital expenditure in the first half of the year. A higher quoted revenue per megawatt therefore does not, by itself, show that a conversion will pay off.
Source: techflowpost.com (originally published 2026-11-12 17:31 UTC+8)